Phasing out SF6 in switchgear: the European timetable
SF6 has insulated and interrupted current in a large share of substations for decades. It is also the most potent greenhouse gas known. The European F-gas Regulation organises its exit from new switchgear, in stages, between 2026 and 2032.

Contents
A very effective gas, and a very problematic one
Sulphur hexafluoride, or SF6, has been used for decades in circuit breakers, switchgear panels and gas-insulated substations. It insulates remarkably well and quenches the electric arc that forms when current is interrupted. It makes compact installations possible, which is valuable in cities and on constrained industrial sites.
Its drawback is major: it is the most potent greenhouse gas known, with a global warming potential tens of thousands of times that of CO2, and an atmospheric lifetime of several thousand years. Every leak counts.
The timetable of Regulation 2024/573
The European regulation on fluorinated greenhouse gases, in force since 2024, prohibits putting into operation new electrical switchgear that uses these gases for insulation or breaking. The ban advances in steps:
| Switchgear | Ban on putting into operation |
|---|---|
| Medium-voltage distribution, up to 24 kV | 1 January 2026 |
| High voltage from 52 to 145 kV, up to 50 kA | 1 January 2028 |
| Medium-voltage distribution, from 24 to 52 kV | 1 January 2030 |
| High voltage above 145 kV or 50 kA | 1 January 2032 |
The text provides for specific cases, in particular when no fluorinated-gas-free solution is available, or for equipment ordered before it came into force. Existing switchgear can keep operating, be repaired and serviced, provided neither the quantity of gas nor its climate impact increases. The official text published on EUR-Lex is authoritative on the details of these conditions.
The alternatives
Manufacturers have developed several families of solutions, which do not perform equally at every voltage:
- dry air or nitrogen for insulation, combined with vacuum interrupters for breaking, especially at medium voltage;
- gas mixtures with a low global warming potential, for higher voltage levels;
- air-insulated designs, bulkier, where space allows.
For extra-high voltage, solutions exist but are more recent, hence the later 2032 deadline.
What it changes in a project
The timetable applies to the date of putting into operation. A substation designed today and energised in three years must therefore already comply with the rule that will apply on that date. In practice:
- check the applicable deadline for each voltage level of the project, against the planned commissioning date;
- adapt the civil works: some SF6-free solutions are bulkier or heavier than the switchgear they replace;
- review operating and maintenance procedures, tooling and team training;
- anticipate procurement lead times, as the whole industry switches to this new equipment at the same time;
- for existing assets, keep the gas inventory, leak checks and end-of-life recovery up to date.
The SF6 phase-out therefore touches substation engineering, procurement and operations at once. It is a long-term undertaking for grid operators, industrial companies and their technical teams through to 2032.
Frequently asked questions
Is SF6 banned in substations?
Not for existing equipment. Regulation (EU) 2024/573 prohibits putting into operation new switchgear that uses fluorinated gases, in stages by voltage, between 2026 and 2032. Installations in service can be operated and maintained.
Since when has medium-voltage SF6 switchgear been affected?
Since 1 January 2026 for distribution switchgear up to and including 24 kV, and from 1 January 2030 between 24 and 52 kV.
What replaces SF6?
Depending on voltage and manufacturer: dry air or nitrogen for insulation, vacuum interrupters for breaking, or gas mixtures with a low global warming potential.
Sources
Read also

Power transformers: why lead times are exploding
A large power transformer used to take about two years to deliver. It now takes up to five. Grid operators book manufacturing slots years in advance, and projects have to build this constraint into their design from day one.
Read the article
From substation to energisation: the stages of a high-voltage project
A high-voltage substation connects a transmission line to an industrial site, a renewable plant or the distribution grid. Building one involves a dozen trades, from grid studies to commissioning tests. Here are the main stages, and the points where a project gains or loses months.
Read the article
Testing and commissioning electrical installations: a profession of its own
Between the end of erection and the first energisation lies a phase that goes unnoticed when it goes well: testing. Yet this is where everything that was designed, built and wired is verified. The test engineer is its guarantor.
Read the article