Testing and commissioning electrical installations: a profession of its own
Between the end of erection and the first energisation lies a phase that goes unnoticed when it goes well: testing. Yet this is where everything that was designed, built and wired is verified. The test engineer is its guarantor.

Contents
The last stage, and the most revealing
A substation, a switchboard or an industrial installation can be perfectly erected and still not behave as intended. A reversed wire, a wrong protection setting, a misconfigured automation: these faults only show up in testing. Finding them at energisation is costly. Finding them later, in operation, can cost far more.
Testing is therefore the moment when everything that was designed, manufactured and installed is verified. The test engineer, or commissioning engineer, is its guarantor.
The stages of a test campaign
Factory tests. Before delivery, the main equipment (transformers, switchgear, control cabinets) is tested at the manufacturer's, often with the client present. It is the first chance to catch a deviation from the specification.
Individual site tests. Once installed, each item is checked on its own: insulation measurements, winding resistance and turns ratio of a transformer, circuit breaker operating times, wiring continuity and labelling, earthing grid.
Functional tests. Next comes checking that the whole system behaves as intended: current and voltage injection into protection relays, tripping, interlocks, automation, signalling and exchanges with the control centre.
Energisation. It follows a programme approved with the operator and, where applicable, the grid operator. Progressive energisation, on-load checks, verification of measurements: every step is recorded.
What digital changes
With digital protection and control based on IEC 61850, some copper wiring is replaced by data exchanges over a network. RTE has begun deploying these systems in its substations.
For the test engineer, this shifts the work: less wiring verification, more checking of configuration files, messages exchanged between devices, time synchronisation and cybersecurity. Tools are changing, and skills with them.
Safety first
Testing takes place on installations moving from construction site to live asset. It is a sensitive period. In France, every intervention falls under the NF C 18-510 standard, which defines authorisations, including for testing operations, and isolation procedures. Rigorous procedures and clear responsibilities between construction and operations are essential.
The file matters as much as the test
A test campaign ends with a file: signed test reports, applied settings, updated drawings, the punch list and proof of its closure. This file is what allows the installation to be accepted, and the operator will rely on it for decades.
A sought-after profile
A test engineer combines knowledge of electrical engineering, grid protection and control systems, real methodological rigour and ease on site. With substation projects, industrial connections and data centers multiplying, and grid operators stepping up investment, this profile is increasingly in demand. Miles Group's current openings reflect it.
Frequently asked questions
What does an electrical test engineer do?
They prepare and carry out the testing of an electrical installation (substation, switchboard, protection, control system) before energisation: checks, measurements, functional tests, test reports and punch-list closure, working with the operator and the grid operator.
What is the difference between individual and functional tests?
Individual tests check each piece of equipment in isolation: insulation, transformer ratio, circuit breaker operating times, wiring. Functional tests check that the whole system behaves as intended: tripping, automation, signalling, remote control.
What authorisation is needed to carry out electrical tests in France?
Testing operations are governed by the NF C 18-510 standard, which defines specific authorisation symbols according to voltage range and type of operation. The employer grants the authorisation after training.
Sources
Read also

From substation to energisation: the stages of a high-voltage project
A high-voltage substation connects a transmission line to an industrial site, a renewable plant or the distribution grid. Building one involves a dozen trades, from grid studies to commissioning tests. Here are the main stages, and the points where a project gains or loses months.
Read the article
Electrifying a factory: what decarbonisation changes on the electrical side
To decarbonise a factory, the first step is to replace fossil fuels with electricity. On paper, it is a change of energy. On site, it is a new electrical project: power multiplied, a customer substation to rethink, a grid connection to negotiate, power quality to control.
Read the article
Phasing out SF6 in switchgear: the European timetable
SF6 has insulated and interrupted current in a large share of substations for decades. It is also the most potent greenhouse gas known. The European F-gas Regulation organises its exit from new switchgear, in stages, between 2026 and 2032.
Read the article